Our workers completed the foundation for the small addition at All Flex in Northfield. It was good that the addition was not any larger, as we were able to work under the tarps and get the foundation completed in spite of some wet weather.
We have moved inside on the trenching project. All Flex uses all sorts of processing materials that they pipe from area to area. With installation of some new equipment they needed the existing concrete floor cut out and a concrete trench constructed. We’ve removed the floor and poured the base of the new trench and are ready to install the sides.